The Northland Railroad Abandons a Portion of the Haliburton Sub
aka
"Congestion at Bell" on My Own Railroad
aka
"Congestion at Bell" on My Own Railroad
Over the past seasons, we have mentioned and discussed the incidents whenever there was congestion at Bell on the IPP&W. Well, Doug has his own form of congestion on his own railroad! The rest of this entry is in Doug's words.
I have been working on the railroad during the
pandemic.
Some of you may remember that I had a few
problems thrown at me as a result of the serious storm in fall of 2018
(remember those tornadoes that were also spawned by the storm). I had
several trees that were broken but fortunately they fell against other trees
and not on the track. As an example, here is a pic of a tree that was
left overhanging the tracks and making the railroad unsafe to operate.
This spring, while April was
mostly cool and wet, May has given time to start work on a railroad that has
been out of action since September 2018.
First up was the removal and disposal of several mature trees. In the picture above you can see the trunk left of the downed tree in the previous pic.
In another area, you can
see three stumps of mature trees that were removed - the track still needs
realignment.
Next was the completion of
flagstone walks. Long ago, I used green
slate for building walks but it then became unavailable. I held back for years but finally decided to
finish using Kingston limestone flags.
After loading by hand 3/4 ton of flagstone at the landscapers, then
unloading here and finally lugging it to the walkway and placing the stones
topped off by moving several hundred kg of stone dust, I can safely say that
I'm too old!
Here is the finished walk.
I'm starting now on track
rehabilitation - all this storm related stuff has left a lot of track misaligned
or slightly damaged. At least the three
main bridges have all survived unscathed.
Here is Watkins Bridge built in aluminum by none other than our own
Lawrence Watkins.
The viaduct in four spans over a
garden is a commercial product by Garden Metals set on piers.
Lastly, a 24 foot three
span truss bridge. I designed and cut the pieces plus sand blasted and spray
painted while my son handled the welding. Now onward with track repairs
- maybe before season's end, Northland trains will be running!
Thanks, Doug for sending this interesting story our way!
Doug's Updated Notes Regarding the Changes to His Railroad
After a long running battle with Mother Nature, the Northland
Railroad conceded defeat and abandoned the trackage of the Haliburton Sub east
of Stone Lantern Junction.
During 2009 and 2010, the railroad built the right of way and
laid track east of Stone Lantern Junction all the way to Haliburton. This effort included the construction of a
new five track car shed with space for 40+ modern standard gauge freight
cars. The right of way encircled a grove
of three large trees as well as passing around several other trees. Operations commenced in late 2010 and for a
time all was well.
By 2014, the emerald ash borer had done its work on the three
large trees contained within the trackage.
A portion of the trackage was temporarily lifted, the benchwork removed
and those trees were felled. The track and
benchwork were reinstalled leaving three big stumps covered now with honeysuckle
and rampant vines.
By the 2017 season, a very
large tree adjacent to the car shed began to exhibit some rot near the base and
it started to lean toward the car shed.
As the operating season wore on the lean became worse. Finally, in September, the narrow gauge cars,
stored in the car shed at Rosseau, were removed to storage and the standard
gauge cars relocated to the now vacant Rosseau car shed. It was not a moment too soon as two weeks
later, during a fall storm, the tree leaned further onto the car shed crushing
a portion of the roof.
Over the winter, the benchwork was removed, the track lifted in that area, the car shed dismantled as best as could be done. The tree was felled in the spring and removed leaving only an enormous stump along with a demolished car shed. The benchwork and track were replaced to allow operations to resume for the 2018 season.
But Mother Nature was not finished. In September, 2018, a violent storm hit Ottawa. Tornadoes did significant damage in the city and although no tornadoes hit the Northland RR, considerable damage ensued as six different trees came down. One broken tree overhung the trackage at Crown Point Yard rendering the railroad unsafe to operate. It remained in that state for the 2019 operating season although several trees were cleared. I reported previously how the problematic tree over the yard was removed in fall 2019 and my progress in rehabilitation trackage working eastward from Crown Point along the Muskoka Sub.
In the area near the now demolished car shed, a tree was blown down. The benchwork was lifted for a third time and the track removed. That tree was cleared in the spring of 2020 leaving a sizeable gap in the trackage of the Haliburton Sub.
As is apparent in this image, there is yet another tree with a significant lean. That tree is currently showing the signs of cracking at the base though it could easily last a century before falling.
On the other hand, I have lost my enthusiasm
for lifting track and benchwork and then rebuilding. Accordingly, the decision was made to abandon
the Haliburton Sub trackage from a point 10 metres east of Stone Lantern
Junction eastward through Haliburton Junction and then Haliburton itself. That will leave sufficient mainline at Stone
Lantern Junction still in place for the quarry train to approach the very steep
8% grade to the Vernon Lake Quarry.
The salvage crews worked in the summer heat this week to lift about 70 metres of track, 6 switches plus a 5 way switch. All that remains is the abandoned right of way awaiting further salvage operations.
Thank you, Doug, for the sharing of this fascinating story!
All the best, Mike Hamer, Ottawa, Ontario, Canada
Thank you, Doug, for sharing what is happening out Manotick way...
ReplyDeleteI only wish I could have been of some help, in your project.
In the past you have on many occasions, contributed greatly to the maintenance on the IPP&W...I wish I had been able to help you.